| General Details | |||
|---|---|---|---|
| Administrative Sanction | Order Number | Dated | Amount(crores) |
| GO (Rt) No. 1096/2013/PWD | 07.08.2013 | 38.95 | |
| Technical Sanction | Order Number | Dated | Amount(crores) |
| GO (Rt) No. 1637/2014/PWD | 27.11.2014 | 31.49 | |
| Revised Administrative Sanction | Order Number | Dated | Amount(crores) |
| GO (Rt) No. 1068/2014/PWD | 31.07.2014 | 38.95 | |
| District | Ernakulam | ||
| LAC | Kalamassery | ||
| Location | |||
| Project Details | |
|---|---|
| Actual Start Date | 24.11.2015 |
| Contractor(s) | M/s RS DEVELOPMENT AND CONSTRUCTIONS (I) PVT LTD |
| Project Management Consultant | KITCO Ltd |
| Category | Road Projects |
| Length | 2700 M |
| Right of way | 45 M |
| No of Lanes | 4 |
| Financial Details | |
|---|---|
| AS Amount(crores) | 38.95 |
| Revised AS Amount(crores) | 38.95 |
| Funded By | Govt Funded |
| Project Outlay(crores) | 136.34 |
| TS Amount(crores) | 31.49 |
| Tender Details | |||
|---|---|---|---|
| Tender No | Dated | Tender Amount(crores) | RBDCK/ APSP ROAD/04/2015 | 07.03.2015 | 28.3 |
| Agreement Details | |||||||
|---|---|---|---|---|---|---|---|
| Agreement No | Agreement Date | Agreed Amount(crores) | Site Handover Date | Period of Completion | Actual Date of Completion | Extended Date of Completion | |
| RBDCK/APSP ROAD/21/2015 | 23.11.2015 | 35.08 | 24.11.2015 | 12 Months | 24.11.2016 | 31.05.2022 | |
| Work Progress Details | |||
|---|---|---|---|
| Physical progress | 95 % | Financial progress | 45.42 % |
| Current status | All works completed in the available land. The project cannot be completed, unless the HMT and NAD lands are obtained. | ||