General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO (Rt) No. 1324/2016/PWD | 27.09.2016 | 25 | |
Technical Sanction | Order Number | Dated | Amount(crores) |
RBDCK/T 301/TS-16/2021-22 | 18.10.2021 | 40.03 | |
Revised Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.132/2017/PWD | 04.02.2017 | 38.88 | |
District | Palakkad | ||
LAC | Malampuzha | ||
Location |
Project Details | |
---|---|
Actual Start Date | 04.01.2021 |
Contractor(s) | M/s SPL Infrastructure Pvt. Ltd |
Project Management Consultant | RITES |
Category | Road Over Bridges |
LC No | 160 |
Railway (km) | 533/8-10 |
Length Including Approaches | 689.71 |
Width of ROB | 10.90 |
GAD Status | APPROVED |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 25 |
Revised AS Amount(crores) | 38.88 |
Funded By | KIIFB |
Project Outlay(crores) | 35.98 |
TS Amount(crores) | 40.03 |
Tender Details | |||
---|---|---|---|
Tender No | Dated | Tender Amount(crores) | RBDCK/ROB/T301/ROB/14 | 25.06.2020 | 222.7 |
Agreement Details | |||||||
---|---|---|---|---|---|---|---|
Agreement No | Agreement Date | Agreed Amount(crores) | Site Handover Date | Period of Completion | Actual Date of Completion | ||
RBDCK/ROB/T44/28/2021 | 04.01.2021 | 251.48 | 12 Months |
Work Progress Details | |||
---|---|---|---|
Physical progress | 80 % | ||
Current status | All Foundation and substructure works are completed up to Piercap. Girder erection and deck slab completed except adjacent span. Drain works 80% completed and retaining wall 95% completed Service Road A2 side upto BC completed (except 60 m) & A1 side service road upto WMM completed Railway portion – All the works are executed directly by Railways. Railways not confirmed the date of completion of railway portion work. Pile and pile cap, Pier, pier cap completed. Girder erection centre span completed |