| General Details | |||
|---|---|---|---|
| Administrative Sanction | Order Number | Dated | Amount(crores) |
| GO (Rt) No. 1324/2016/PWD | 27.09.2016 | 25 | |
| Technical Sanction | Order Number | Dated | Amount(crores) |
| RBDCK/T 301/TS-16/2021-22 | 18.10.2021 | 40.03 | |
| Revised Administrative Sanction | Order Number | Dated | Amount(crores) |
| GO(Rt)No.132/2017/PWD | 04.02.2017 | 38.88 | |
| District | Palakkad | ||
| LAC | Malampuzha | ||
| Location | |||
| Project Details | |
|---|---|
| Actual Start Date | 04.01.2021 |
| Contractor(s) | M/s SPL Infrastructure Pvt. Ltd |
| Project Management Consultant | RITES |
| Category | Road Over Bridges |
| LC No | 160 |
| Railway (km) | 533/8-10 |
| Length Including Approaches | 689.71 |
| Width of ROB | 10.90 |
| GAD Status | APPROVED |
| No of Lanes | 2 |
| Financial Details | |
|---|---|
| AS Amount(crores) | 25 |
| Revised AS Amount(crores) | 38.88 |
| Funded By | Government |
| Project Outlay(crores) | 35.98 |
| TS Amount(crores) | 40.03 |
| Tender Details | |||
|---|---|---|---|
| Tender No | Dated | Tender Amount(crores) | RBDCK/ROB/T301/ROB/14 | 25.06.2020 | 222.7 |
| Agreement Details | |||||||
|---|---|---|---|---|---|---|---|
| Agreement No | Agreement Date | Agreed Amount(crores) | Site Handover Date | Period of Completion | Actual Date of Completion | ||
| RBDCK/ROB/T44/28/2021 | 04.01.2021 | 251.48 | 12 Months | ||||
| Work Progress Details | |||
|---|---|---|---|
| Physical progress | 80 % | ||
| Current status | All Foundation and substructure works are completed up to Piercap. Girder erection and deck slab completed except adjacent span. Retaining wall upto bracket portion completed. A1 side approcah road works upto WMM completed. Balance service road, Drainage and approach road works are in progress. Railway Portion - All works executed directly by Railways. Girder erection completed, slab 1/3 completed. Balance works in progress. | ||