Vadanamkurussi ROB

Back View Progress

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.1324/2016/PWD 27.09.2016 10
Technical Sanction Order Number Dated Amount(crores)
RBDCK/T 301/TS-17/2021-22 18.10.2021 29.01
Revised Administrative Sanction Order Number Dated Amount(crores)
GO (Rt)No.697/2017/PWD 24.05.2017 34.79
District Palakkad
LAC Pattambi
Location
Project Details
Actual Start Date 04.01.2021
Contractor(s) M/s SPL Infrastructure Pvt. Ltd
Project Management Consultant RITES
Category Road Over Bridges
LC No 2
Railway (km) 4/100-200
Length Including Approaches 584.67
Width of ROB 10.15
GAD Status APPROVED
No of Lanes 2
Financial Details
AS Amount(crores) 10
Revised AS Amount(crores) 34.79
Funded By KIIFB
Project Outlay(crores) 30.09
TS Amount(crores) 29.01
Tender Details
Tender No Dated Tender Amount(crores)
RBDCK/ROB/T301/ROB/14 25.06.2020 222.7
Agreement Details
Agreement No Agreement Date Agreed Amount(crores) Site Handover Date Period of Completion Actual Date of Completion
RBDCK/ROB/T44/28/2021 04.01.2021 251.48 12 Months
Work Progress Details
Physical progress 70 %
Current status All Foundation and substructure completed up to Pier cap. Pedestal underpass work completed. 15/15 Girder erection completed.15/15 deck slab completed. Retaining wall, drainage & service road works are in progress. Railway portion - Pile, Pile cap, pier, pier cap & girder erection completed. Slab works in progress.
View Progress