| General Details | |||
|---|---|---|---|
| Administrative Sanction | Order Number | Dated | Amount(crores) |
| GO(Rt)No.1324/2016/PWD | 27.09.2016 | 10 | |
| Technical Sanction | Order Number | Dated | Amount(crores) |
| RBDCK/T 301/TS-17/2021-22 | 18.10.2021 | 29.01 | |
| Revised Administrative Sanction | Order Number | Dated | Amount(crores) |
| GO (Rt)No.697/2017/PWD | 24.05.2017 | 34.79 | |
| District | Palakkad | ||
| LAC | Pattambi | ||
| Location | |||
| Project Details | |
|---|---|
| Actual Start Date | 04.01.2021 |
| Contractor(s) | M/s SPL Infrastructure Pvt. Ltd |
| Project Management Consultant | RITES |
| Category | Road Over Bridges |
| LC No | 2 |
| Railway (km) | 4/100-200 |
| Length Including Approaches | 584.67 |
| Width of ROB | 10.15 |
| GAD Status | APPROVED |
| No of Lanes | 2 |
| Financial Details | |
|---|---|
| AS Amount(crores) | 10 |
| Revised AS Amount(crores) | 34.79 |
| Funded By | Government |
| Project Outlay(crores) | 30.09 |
| TS Amount(crores) | 29.01 |
| Tender Details | |||
|---|---|---|---|
| Tender No | Dated | Tender Amount(crores) | RBDCK/ROB/T301/ROB/14 | 25.06.2020 | 222.7 |
| Agreement Details | |||||||
|---|---|---|---|---|---|---|---|
| Agreement No | Agreement Date | Agreed Amount(crores) | Site Handover Date | Period of Completion | Actual Date of Completion | ||
| RBDCK/ROB/T44/28/2021 | 04.01.2021 | 251.48 | 12 Months | ||||
| Work Progress Details | |||
|---|---|---|---|
| Physical progress | 85 % | ||
| Current status | All works upto deck slab completed. Diaphragm (17/17) completed. Balance Retaining wall, drainage & service road works are in progress. Railway Portion - Slab works completed and finishing works in progress. | ||