Projects

Kottikkulam ROB

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.1324/2016/PWD 27.09.2016 10
Technical Sanction Order Number Dated Amount(crores)
RBDCK/ T 150/ TS - 05/ 2023-24 06.12.2023
Revised Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.132/2017/PWD 04.02.2017 23.97
District Kasargod
LAC Udma
Location
Project Details
LA status Not Completed
Project Management Consultant KITCO Ltd
Category Road Over Bridges
LC No 280
Railway (km) 831/700-800
Length Including Approaches 262.50
Width of ROB 10.05
GAD Status APPROVED
No of Lanes 2
Financial Details
AS Amount(crores) 10
Revised AS Amount(crores) 23.97
Funded By Government
Project Outlay(crores) 19.6
Tender Details
Tender No Dated Tender Amount(crores)
RBDCK/ ROB/ T 150/ 302/ 2024 16.02.2024 14.31
RBDCK/ ROB/ T 150/325/ 2024 27.06.2024 14.31
Work Progress Details
Current status The DPR was approved by KIIFB on 16.05.2017 for an amount of Rs. 19.6 crore. The major portion of the required land had already been acquired by the Railways. The Railways granted permission to RBDCK to carry out works on the acquired railway land on 27.02.2023, and the GAD was approved by the Railways on 13.01.2023. To suit the revised GAD, additional land acquisition is required, and the process is in progress. The 4(1) notification was published on 01.07.2024, and the 11(1) notification was published on 16.07.2025. The work was first tendered on 17.02.2024, but no bids were received. Subsequently, it was re-tendered on 27.06.2024, and one bid was received. The financial bid was opened on 22.10.2024. Since the quoted amount was 21.56% higher than the estimate amount and 2.92% higher than the LMR amount, RBDCK requested tender approval from the Secretary, PWD on 04.12.2024 and again on 09.04.2025. On 12.06.2025, the Government suggested re-tendering the work. Accordingly, the estimate was revised based on DSR 2021, and the TS Committee conducted its review and issued TS on 18.07.2025. Subsequently, a revised FS for Rs. 22.83 crore was approved by KIIFB on 01.09.2025, and the work was re-tendered on 19.09.2025. The pre-qualification bid was opened on 04.11.2025, and the documents are under evaluation.