General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.1324/2016/PWD | 27.09.2016 | 40 | |
Revised Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.699/2017/PWD | 24.05.2017 | 43.47 | |
District | Thrissur | ||
LAC | Puthukkad |
Project Details | |
---|---|
Actual Start Date | 09.10.2017 |
Project Management Consultant | KITCO Ltd |
Category | Road Over Bridges |
LC No | 28 & 29 |
Railway (km) | 46/9-10 |
Length Including Approaches | 592.15 m |
Width of ROB | 10.20 m |
GAD Status | Not approved |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 40 |
Revised AS Amount(crores) | 43.47 |
Funded By | KIIFB |
Project Outlay(crores) | 37.73 |
Work Progress Details | |||
---|---|---|---|
Physical progress | 75 % | ||
Current status | DPR approved by KIIFB on 27.07.2017 for an amount of Rs. 37.71 Crores. Modified LA requisition submitted to Dt. Collector Thrissur on 01.11.2019. Land taken possession completed on 14.09.2022. Final GAD submitted to Railways on 22.02.2022. Vide letter dated 11.07.2022, Railway informed that GAD of ROB’s between Ernakulam and Shornur will be approved only after finalization of 3rd line. Revised GAD approved by Railways on 28.11.2024. Revised Estimate under preparation. |