Current status |
DPR approved by KIIFB on 27.07.2017 for an amount of Rs.47.72 Cr. GAD approved on 29.01.2021.
Land taken possession 25.01.2025.
The work was tendered on 10.02.2025, but only a Single bid received. Hence the work was retendered on 19.03.2025. Technical bid opened on 29.04.2025, one bid received. Financial bid opened on 17.05.2025. Vide GO(Rt)No. 47/2025/FIN dated 11.04.2025 goverment issued orders for acceptance of bid where estimate is prepared SoR prior to the Introduction of DSoR 2021, but tender procedures are finalised after the applicability of DSoR 2021.
Tender accpetance committee convened on 23.06.2025 and decided to award the work to L1 bidder, M/s Cheriyan Varkey Constructions company.pvt Ltd. |