Current status |
Agreement was executed with M/s ULCCS for an amount of Rs. 48.83 Cr on 20.04.2023. NTP issued on 28.04.2023.
GoK is planning to use UHPFRC (ULTRA HIGH PERFORMANCE FIBRE REINFORCED CONCRETE) technology for new bridge construction in Kerala and RBDCK has planned to adopt this Technology in the construction Thirunnavaya Bridge. GoK directed to form, Advisory Committee, Implementation Committee & Technical Committee. Accordingly RBDCK had formed Implementation Committee and Technical Committee. Preparation of Design & drawings is completed and submitted to TS committee. Initial pile load test completed. Technical committee was convened on 16.08.2024 & 18.10.2024.
Regarding the alignment of Thirunavaya –Thavanur River bridge a petition was submitted on Hon'ble High Court by Dr. E Sreedharan. Hon'ble High Court directed on 03.10.2024 that the PWD Secretary will examine the suggestions given by the Petitioner and thereafter taken an appropriate decision. Accordingly RBDCK had requested PWD Secretary to hear petitioner at the earliest. PWD Secretary visited site & heard Dr. E Sreedharan on 26.11.2024.
During the hearing, Dr. E. Sreedharan proposed a new alignment option that differed from the option submitted by Dr. E. Sreedharan to the Hon'ble court. Based on this suggestion, the Secretary, PWD directed RBDCK to study the new alignment and show this to Dr. E. Sreedharan.As per the direction of Secretary, PWD, RBDCK has prepared new alignment sketche and a comparison reports were shown to Dr. E. Sreedharan on 19.12.2024 and same report was submitted on 23.12.2024 to Secretary, PWD. Government has decided to reject Dr. E Sreedharan's request for an alignment change on 11.03.2025. Accordingly RBDCK directed M/s ULCCS to start the work on 20.03.2025. |