General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.1324/2016/PWD | 27.09.2016 | 20 | |
Technical Sanction | Order Number | Dated | Amount(crores) |
RBDCK/T 203/TS-04/2022-23 | 01.08.2022 | 33.54 | |
Revised Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.878/2018/PWD | 19.05.2018 | 80.42 | |
District | Kottayam | ||
LAC | Kanjirappally |
Project Details | |
---|---|
Actual Start Date | 10.08.2023 |
Contractor(s) | Backbone Construction Pvt. Ltd. |
Project Management Consultant | RITES |
Category | Road Projects |
Length | 1.626 km |
Right of way | 14.00m |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 20 |
Revised AS Amount(crores) | 80.42 |
Funded By | KIIFB |
Project Outlay(crores) | 78.69 |
TS Amount(crores) | 33.54 |
Tender Details | |||
---|---|---|---|
Tender No | Dated | Tender Amount(crores) | RBDCK/ RW/ T203/ 237/ 2023 | 13.03.2023 | 26.6 |
Agreement Details | |||||||
---|---|---|---|---|---|---|---|
Agreement No | Agreement Date | Agreed Amount(crores) | Site Handover Date | Period of Completion | Actual Date of Completion | ||
RBDCK/T 203/78/2023 | 03.08.2023 | 26.16 | 10.08.2023 | 18 |
Work Progress Details | |||
---|---|---|---|
Physical progress | 36 % | ||
Current status | Earthwork excavation, filling, hard rock excavation and culvert works up to deck slab completed. DR work completed. Bridge Design submitted to IIT for Vetting. Bridge foundation A1 raft work completed. A2 raft reinforcement, Abutment wall, GSB, WMM works in progress. |