Current status |
DPR approved on 15.05.2018. LA requisition submitted on 4.09.2018. Boundary stone planting completed and Site inspection conducted. 4(1) notification published on 03.12.2019. 11(1) Notification published on 18.02.2021. Joint verification by LAO and RBDCK officials was conducted on 09.12.2021 & 14.12.2021. As per G.O(P) No.364/2022/RD dated 08.04.2022, the time for publication of 19(1) declaration was extended for 6 months from 18.02.2022. LA cost released to LAO on 23.07.2022. 19(1) declaration published on 12.08.2022. 76% of Land possession is completed. Balance is in progress. |