General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO (Rt)No.942/2017/PWD | 10.07.2017 | 30 | |
District | Thrissur | ||
LAC | Ollur |
Project Details | |
---|---|
Actual Start Date | 23.01.2019 |
Project Management Consultant | KITCO Ltd |
Category | Road Over Bridges |
LC No | 24 |
Railway (km) | 35/7-8 |
Length Including Approaches | 750 m |
Width of ROB | 10.20 m |
GAD Status | APPROVED |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 30 |
Funded By | KIIFB |
Project Outlay(crores) | 31.042 |
Work Progress Details | |||
---|---|---|---|
Physical progress | 50 % | ||
Current status | DPR approved by KIIFB on 26.10.2018 for an amount of Rs.31.042 Cr. Revised requisition including new survey numbers submitted to DC and LAO on 18.08.2020. LA nearing completion. GAD was already approved. Vide letter dated 11.07.2022, Railway informed that GAD of ROB’s between Ernakulam and Shornur will be approved only after finalization of 3rd line. Revised GAD approved on 18.11.2024. TS for construction issued on 07.01.2024. Revised F.S issued by KIIFB on 24.03.2025. The work was Tendered on 29.03.2025 |