| General Details | |||
|---|---|---|---|
| Administrative Sanction | Order Number | Dated | Amount(crores) |
| GO (Rt) No. 942/2017/PWD | 10.07.2017 | 90 | |
| Technical Sanction | Order Number | Dated | Amount(crores) |
| RBDCK/T 146/TS-17/2024-25 | 30.10.2024 | 72.96 | |
| District | Kottayam | ||
| LAC | Changanassery | ||
| Location | |||
| Project Details | |
|---|---|
| Contractor(s) | M/s ULCCS |
| Project Management Consultant | RITES |
| Category | Flyover |
| Length including approaches | 1060 |
| Width of Flyover | 9 |
| No of Lanes | 2 |
| Financial Details | |
|---|---|
| AS Amount(crores) | 90 |
| Funded By | KIIFB |
| Project Outlay(crores) | 85.68 |
| TS Amount(crores) | 72.96 |
| Tender Details | |||
|---|---|---|---|
| Tender No | Dated | Tender Amount(crores) | RBDCK/FLY/T 146/385/2025 | 29.03.2025 | 57.41 |
| Agreement Details | |||||||
|---|---|---|---|---|---|---|---|
| Agreement No | Agreement Date | Agreed Amount(crores) | Site Handover Date | Period of Completion | Actual Date of Completion | ||
| RBDCK/T 146/8/2025 | 07.11.2025 | 61.54 | 20.12.2025 | 24 | 19.12.2027 | ||
| Work Progress Details | |||
|---|---|---|---|
| Current status | DPR approved by KIIFB on 11.02.2020 for an amount of Rs.62.11 Cr. Land taken possession 65/69 completed. Balance pending due to WP(C) 39771/2022. TS committe was held on 30.10.2024 and recommented to issue technical sanction for the estimate amounting to Rs. 72,96,45,445.20. Revised F.S issued by KIIFB on 23.03.2025. Work tendered on 29.03.2025. 3 bids received. Financial bid opened on 06-06-2025. Work awarded and LOA issued to the contractor on 24.09.2025. Agreement executed on 06.11.2025. NTP issued on 20.12.2025. Topographic survey completed. Soil Investigation in progress. | ||