Current status |
DPR approved on 26.10.2018 for an amount of Rs.28.5 Cr. Land taking possession completed on 16.10.2023. GAD approved by Railways on 08.08.2022. Land transfer of Government land completed on 26.07.2024.
TS committee approved estimate and accorded Technical Sanction on 29.01.2024. KIIFB accorded revised financial sanction on 27.11.2024. The work was tendered on 30.01.2025. Technical Bid opened on 15.03.25 and 4 Bids received. Financial bid opened on 21.05.2025. Letter submitted to ULCCS for negotiation. |