Current status |
GAD approved by Railways on 12.07.2022. LA Requisition submitted to District Collector, Alappuzha and request for Revenue (B) Sanction submitted to Secretary PWD on 30.07.2022. Revenue Sanction for LA received vide G.O.(Rt)No.3601/2022/RD dated 25.08.2022. District Collector appointed Special Tahsildar LA KIIFB Kayamkulam as Land Acquisition Officer for the project on 15.09.2022. 6(1) notification published on 24.09.2022. Stone planting completed and Joint inspection conducted on 19.10.2022. Contigency charge of Rs.50 lakhs released to LAO on 21.11.2022. SIA public hearing completed on 17.01.2023. Expert committee report submitted to DC. SIA study completed. 11(1) published on 15.03.2023. LA cost released to LAO. 19(1) published on 22.11.2023. Land taken possession completed on 05/03/2024. Technical sanction committee will be convened within 1 month. |