Current status |
DPR approved on 09.08.2020 for an amount of Rs. 38.22 Cr. GAD approved by Railways on 12.07.2022.
11(1) published on 15.03.2023. LA cost released to LAO. 19(1) published on 22.11.2023. Land taken possession completed on 05/03/2024. TS issued on 09.07.2024. Request for revised Financial sanction submitted to KIIFB on 30/07/2024. Demolition of structures and tree cutting is completed. Vide order no PWD 011-15/APR-3/2024/KIIFB dated 23.11.2024, KIIFB has accorded sanction for revised FS of Rs. 48.33 Cr. |