| General Details | |||
|---|---|---|---|
| Administrative Sanction | Order Number | Dated | Amount(crores) |
| GO (Rt) No. 942/2017/PWD | 10.07.2017 | 20 | |
| District | Palakkad | ||
| LAC | Nenmara | ||
| Location | |||
| Project Details | |
|---|---|
| Contractor(s) | |
| Category | River Bridges |
| No of Lanes | 2 |
| Financial Details | |
|---|---|
| AS Amount(crores) | 20 |
| Funded By | KIIFB |
| Project Outlay(crores) | 10.61 |
| Work Progress Details | |||
|---|---|---|---|
| Physical progress | 20 % | ||
| Current status | DPR approved by KIIFB on 11.02.2020 for an amount of Rs.10.61 Cr . LA Completed. Work was retendered on 19.02.2025. One bid received and accepted the same with concurrence of MD as its within permissible limit. Agreement was executed with M/s Baab Constructions India Pvt on 28.10.2025. Foundation and substructure works in progress. Girder casting in progress. | ||