Airport Seaport Road Phase II (HMT TO NAD)

Back View Gallery View Progress

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO (Rt) No. 1096/2013/PWD 07.08.2013 38.95
Technical Sanction Order Number Dated Amount(crores)
GO (Rt) No. 1637/2014/PWD 27.11.2014 31.49
Revised Administrative Sanction Order Number Dated Amount(crores)
GO (Rt) No. 1068/2014/PWD 31.07.2014 38.95
District Ernakulam
LAC Kalamassery
Location
Project Details
Actual Start Date 24.11.2015
Contractor(s) M/s RS DEVELOPMENT AND CONSTRUCTIONS (I) PVT LTD
Project Management Consultant KITCO Ltd
Category Road Projects
Length 2700 M
Right of way 45 M
No of Lanes 4
Financial Details
AS Amount(crores) 38.95
Revised AS Amount(crores) 38.95
Funded By Govt Funded
Project Outlay(crores) 136.34
TS Amount(crores) 31.49
Tender Details
Tender No Dated Tender Amount(crores)
RBDCK/ APSP ROAD/04/2015 07.03.2015 28.3
Agreement Details
Agreement No Agreement Date Agreed Amount(crores) Site Handover Date Period of Completion Actual Date of Completion Extended Date of Completion
RBDCK/APSP ROAD/21/2015 23.11.2015 35.08 24.11.2015 12 Months 24.11.2016 31.05.2022
Work Progress Details
Physical progress 95 % Financial progress 45.42 %
Current status The work of 1.54 km (excluding the HMT stretch of 600 m and the NAD stretch of 560 m) was completed in 2022 at a cost of ₹24 Crores. However, the project could not be completed earlier as the HMT and NAD lands were yet to be obtained. Now, the HMT and NAD lands have been handed over to RBDCK Ltd. RBDCK had requested the Government of Kerala for Administrative Sanction for an amount of ₹49,57,61,616.07/- (₹32,26,93,115/- for NAD land and ₹17,30,68,501.07/- for balance road construction). The Government of Kerala granted Administrative Sanction on 15.05.2025 for an amount of ₹32,26,00,000/- for NAD land. Subsequently, RBDCK requested the Government for Revised Administrative Sanction on 03.10.2025. Vide G.O. (Rt) No. 5/2026/PWD dated 03.01.2026, the Government accorded Administrative Sanction for an amount of ₹21,40,52,415/-. Accordingly, Technical Sanction for ₹20,33,49,793.32 was accorded on 16.01.2026. Tender for the balance work was invited on 12.02.2026. However, only one bidder participated, and hence the tender was re-invited on 17.02.2026.The technical bids were opened on 03.03.2026, and three bids were received. After technical evaluation, two bidders were found qualified, while one bidder was rejected due to inability to meet the minimum qualification criteria. The financial bids were opened on 10.03.2026. The L1 bidder quoted an amount higher than the admissible amount; therefore, negotiation was requested with the L1 bidder on 16.03.2026.