General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO (Rt) No. 1096/2013/PWD | 07.08.2013 | 38.95 | |
Technical Sanction | Order Number | Dated | Amount(crores) |
GO (Rt) No. 1637/2014/PWD | 27.11.2014 | 31.49 | |
Revised Administrative Sanction | Order Number | Dated | Amount(crores) |
GO (Rt) No. 1068/2014/PWD | 31.07.2014 | 38.95 | |
District | Ernakulam | ||
LAC | Kalamassery | ||
Location |
Project Details | |
---|---|
Actual Start Date | 24.11.2015 |
Contractor(s) | M/s RS DEVELOPMENT AND CONSTRUCTIONS (I) PVT LTD |
Project Management Consultant | KITCO Ltd |
Category | Road Projects |
Length | 2700 M |
Right of way | 45 M |
No of Lanes | 4 |
Financial Details | |
---|---|
AS Amount(crores) | 38.95 |
Revised AS Amount(crores) | 38.95 |
Funded By | Govt Funded |
Project Outlay(crores) | 136.34 |
TS Amount(crores) | 31.49 |
Tender Details | |||
---|---|---|---|
Tender No | Dated | Tender Amount(crores) | RBDCK/ APSP ROAD/04/2015 | 07.03.2015 | 28.3 |
Agreement Details | |||||||
---|---|---|---|---|---|---|---|
Agreement No | Agreement Date | Agreed Amount(crores) | Site Handover Date | Period of Completion | Actual Date of Completion | Extended Date of Completion | |
RBDCK/APSP ROAD/21/2015 | 23.11.2015 | 35.08 | 24.11.2015 | 12 Months | 24.11.2016 | 31.05.2022 |
Work Progress Details | |||
---|---|---|---|
Physical progress | 95 % | Financial progress | 45.42 % |
Current status | All works completed in the available land. The project cannot be completed, unless the HMT and NAD lands are obtained. |