| General Details | |||
|---|---|---|---|
| Administrative Sanction | Order Number | Dated | Amount(crores) |
| GO (Rt) No. 1324/2016/PWD | 27.09.2016 | 25 | |
| Technical Sanction | Order Number | Dated | Amount(crores) |
| RBDCK/T 301/TS-16/2021-22 | 18.10.2021 | 40.03 | |
| Revised Administrative Sanction | Order Number | Dated | Amount(crores) |
| GO(Rt)No.132/2017/PWD | 04.02.2017 | 38.88 | |
| District | Palakkad | ||
| LAC | Malampuzha | ||
| Location | |||
| Project Details | |
|---|---|
| Actual Start Date | 04.01.2021 |
| Contractor(s) | M/s SPL Infrastructure Pvt. Ltd |
| Project Management Consultant | RITES |
| Category | Road Over Bridges |
| LC No | 160 |
| Railway (km) | 533/8-10 |
| Length Including Approaches | 689.71 |
| Width of ROB | 10.90 |
| GAD Status | APPROVED |
| No of Lanes | 2 |
| Financial Details | |
|---|---|
| AS Amount(crores) | 25 |
| Revised AS Amount(crores) | 38.88 |
| Funded By | Government |
| Project Outlay(crores) | 35.98 |
| TS Amount(crores) | 40.03 |
| Tender Details | |||
|---|---|---|---|
| Tender No | Dated | Tender Amount(crores) | RBDCK/ROB/T301/ROB/14 | 25.06.2020 | 222.7 |
| Agreement Details | |||||||
|---|---|---|---|---|---|---|---|
| Agreement No | Agreement Date | Agreed Amount(crores) | Site Handover Date | Period of Completion | Actual Date of Completion | ||
| RBDCK/ROB/T44/28/2021 | 04.01.2021 | 251.48 | 12 Months | ||||
| Work Progress Details | |||
|---|---|---|---|
| Physical progress | 80 % | ||
| Current status | All major works upto deck slab completed except A2 side deck slab. A1 side approcah road works upto WMM and A2 approach road upto embankmet completed. Balance service road, Drainage, Deck slab,Diaphram and approach road works are in progress. Railway Portion - All works completed. | ||