Projects

Akathethara ROB

Back View Gallery View Progress

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO (Rt) No. 1324/2016/PWD 27.09.2016 25
Technical Sanction Order Number Dated Amount(crores)
RBDCK/T 301/TS-16/2021-22 18.10.2021 40.03
Revised Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.132/2017/PWD 04.02.2017 38.88
District Palakkad
LAC Malampuzha
Location
Project Details
Actual Start Date 04.01.2021
Contractor(s) M/s SPL Infrastructure Pvt. Ltd
Project Management Consultant RITES
Category Road Over Bridges
LC No 160
Railway (km) 533/8-10
Length Including Approaches 689.71
Width of ROB 10.90
GAD Status APPROVED
No of Lanes 2
Financial Details
AS Amount(crores) 25
Revised AS Amount(crores) 38.88
Funded By KIIFB
Project Outlay(crores) 35.98
TS Amount(crores) 40.03
Tender Details
Tender No Dated Tender Amount(crores)
RBDCK/ROB/T301/ROB/14 25.06.2020 222.7
Agreement Details
Agreement No Agreement Date Agreed Amount(crores) Site Handover Date Period of Completion Actual Date of Completion
RBDCK/ROB/T44/28/2021 04.01.2021 251.48 12 Months
Work Progress Details
Physical progress 70 %
Current status All Foundation and substructure works are completed up to Piercap (excluding railway portion). Girder erection and deck slab completed except adjacent span. Girder erection & deck slab concrete for adjacent span can be completed only after the completion of railway span. Drain works 80% completed and retaining wall 85% completed. Service road works & Approach road works are in progress. Railway portion – All the works are executed directly by Railways. Railways not confirmed the date of completion of railway portion work. Piling works completed. 1/4 Pile cap completed. Balance work in progress.
View Gallery View Progress