| General Details | |||
|---|---|---|---|
| Administrative Sanction | Order Number | Dated | Amount(crores) |
| GO(Rt)No.1324/2016/PWD | 27.09.2016 | 10 | |
| Technical Sanction | Order Number | Dated | Amount(crores) |
| RBDCK/ T 155/ TS - 03/ 2023-24 | 16.10.2023 | 29.01 | |
| Revised Administrative Sanction | Order Number | Dated | Amount(crores) |
| G.O. (Rt)No.698/2017/PWD | 24.05.2017 | 32.6 | |
| District | Malappuram | ||
| LAC | Tirurangadi | ||
| Location | |||
| Project Details | |
|---|---|
| Contractor(s) | M Rajkumar and Onyx Construction (JV) |
| Project Management Consultant | RITES |
| Category | Road Over Bridges |
| LC No | 174-B |
| Railway (km) | 642/500-600 |
| Length Including Approaches | 370.18m |
| Width of ROB | 10.15m |
| GAD Status | APPROVED |
| No of Lanes | 2 |
| Financial Details | |
|---|---|
| AS Amount(crores) | 10 |
| Revised AS Amount(crores) | 32.6 |
| Funded By | KIIFB |
| TS Amount(crores) | 29.01 |
| Tender Details | |||
|---|---|---|---|
| Tender No | Dated | Tender Amount(crores) | RBDCK/ROB/T155/287/2023 | 16.12.2023 | 24.59 |
| Work Progress Details | |||
|---|---|---|---|
| Physical progress | 20 % | ||
| Current status | Piling works 50/51 completed. Balance pile and pile cap works in progress. A1 abutment works in progress. Railway Work - Entrusted RBDCK for works upto Pier Cap. Piling, pile cap, pier and 1/2 pier cap works completed. Remaining one Railway pier cap works in progress. Fabrication of approch span pier works are progressing at fabrication yard | ||