General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.1324/2016/PWD | 27.09.2016 | 10 | |
Technical Sanction | Order Number | Dated | Amount(crores) |
RBDCK/ T 155/ TS - 03/ 2023-24 | 16.10.2023 | 29.01 | |
Revised Administrative Sanction | Order Number | Dated | Amount(crores) |
G.O. (Rt)No.698/2017/PWD | 24.05.2017 | 32.6 | |
District | Malappuram | ||
LAC | Tirurangadi | ||
Location |
Project Details | |
---|---|
Contractor(s) | M Rajkumar and Onyx Construction (JV) |
Project Management Consultant | RITES |
Category | Road Over Bridges |
LC No | 174-B |
Railway (km) | 642/500-600 |
Length Including Approaches | 370.18m |
Width of ROB | 10.15m |
GAD Status | APPROVED |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 10 |
Revised AS Amount(crores) | 32.6 |
Funded By | KIIFB |
TS Amount(crores) | 29.01 |
Tender Details | |||
---|---|---|---|
Tender No | Dated | Tender Amount(crores) | RBDCK/ROB/T155/287/2023 | 16.12.2023 | 24.59 |
Work Progress Details | |||
---|---|---|---|
Physical progress | 1 % | ||
Current status | Work tendered on 27.10.2023. Technical bid was opened on 08.12.2023. Single bid received. Work retendered on 16/12/2023. Technical bid opened and evaluation completed. Financial bid opened on 06/03/2024. LOA issued on 12/03/2024. Performance Security and 50% of Additional Performance Security submitted. The contractor also requested 3 months time to submit the balance 50% and requested to execute the agreement. Agreement executed on 07/08/2024. NTP issued on 14.08.2024. Clearing and grubbing in progress. Co-ordinates marking in the presence of Railway officials completed. Clearing, grubbing and mobilisation works in progress. |