Projects

Edava ROB

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.1324/2016/PWD 27.09.2016 15
Revised Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.132/2017/PWD 04.02.2017 35.69
District Thiruvananthapuram
LAC Varkala
Location
Project Details
Actual Start Date 13.07.2017
Project Management Consultant KITCO Ltd
Category Road Over Bridges
LC No 555
Railway (km) 175/000-100
Length Including Approaches 596.90
Width of ROB 10.50
GAD Status APPROVED
No of Lanes 2
Financial Details
AS Amount(crores) 15
Revised AS Amount(crores) 35.69
Funded By KIIFB
Project Outlay(crores) 25.23
Work Progress Details
Physical progress 82 %
Current status DPR approved. LA request submitted to Dist. collector 29.08.2018. LA is in final stage. 19(1) notification published on 16.11.2021. On 02.12.2022 Hon'ble High court stayed the taking possession of 12 petitioners of WP(c) 28008/2020. LA taking possession of 51/69 completed on 27.05.2023. On 12.02.2024, Hon'ble HC disposed of the petitions filed by residents of Edava, directing the district collector to "reconsider the matter after giving an opportunity of hearing to the petitioners"" within 2 months. On 13.05.2024, the District Collector issued orders disposing off the petitions and directed the Revenue dept. to complete the remaining LA works. On WP(C) 19439/2024, 21115/2024, before Hon'ble HC of Kerala, the court stayed all orders for 1 month. On 24.09.2024, the Hon'ble High Court disposed all the petitioners. But the petitioners had filed writ appeal against the order in Hon'ble High Court. On 16.10.2024, the Hon'ble HC has disposed the writ appeal. On 23.10.2024, an SLP was filed by 6 residents of Edava before the Hon'ble Supreme Court of India. The Supreme Court has stayed all process of land acquisition.