Current status |
Agreement was executed with M/s ULCCS for an amount of Rs. 48.83 Cr on 20.04.2023. NTP issued on 28.04.2023. Preparation of Design & drawings are completed and submitted to TS committee. Initial pile load test completed. Technical committee was convened on 16.08.2024 & 18.10.2024.
Regarding the alignment of Thirunavaya –Thavanur River bridge a petition was submitted on Hon'ble High Court by Dr. E Sreedharan. Hon'ble High Court directed on 03.10.2024 that the PWD Secretary will examine the suggestions given by the Petitioner and thereafter taken an appropriate decision. PWD Secretary visited site & heard Dr. E Sreedharan on 26.11.2024.
During the hearing, Dr. E. Sreedharan proposed a new alignment option that differed from the option submitted by Dr. E. Sreedharan to the Hon'ble court. Based on this suggestion, the Secretary, PWD directed RBDCK to study the new alignment and present it to Dr. E. Sreedharan. RBDCK has prepared new alignment sketches and a comparison reports were shown to Dr. E. Sreedharan on 19.12.2024 and same report was submitted on 23.12.2024 to Secretary, PWD. |