General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.73/2017/PWD | 16.01.2017 | 50 | |
Technical Sanction | Order Number | Dated | Amount(crores) |
RBDCK/T 42/TS-07/2020-21 | 15.02.2021 | 48.52 | |
Revised Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.1066/2017/PWD | 22.07.2017 | 63.86 | |
District | Malappuram | ||
LAC | Tirur , Thavanur |
Project Details | |
---|---|
Actual Start Date | 28.04.2023 |
Contractor(s) | Uralungal Labour Contract Co-operative Society Ltd |
Project Management Consultant | RITES |
Category | River Bridges |
Length including approaches | 1180 |
Width of Bridge | 11 |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 50 |
Revised AS Amount(crores) | 63.86 |
Funded By | KIIFB |
Project Outlay(crores) | 53.38 |
TS Amount(crores) | 48.52 |
Tender Details | |||
---|---|---|---|
Tender No | Dated | Tender Amount(crores) | RBDCK/ T42/132 / 2021 | 05.08.2021 | 42.88 |
Agreement Details | |||||||
---|---|---|---|---|---|---|---|
Agreement No | Agreement Date | Agreed Amount(crores) | Site Handover Date | Period of Completion | Actual Date of Completion | ||
RBDCK/T 42/74/2023 | 20.04.2023 | 48.83 | 28.04.2023 | 18 months |
Work Progress Details | |||
---|---|---|---|
Current status | Agreement was executed with M/s ULCCS for an amount of Rs. 48.83 Cr on 20.04.2023. NTP issued on 28.04.2023. Preparation of Design & drawings are completed and submitted to TS committee. Initial pile load test pile boring completed. |