Projects

Thirunavaya-Thavanur River Bridge

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.73/2017/PWD 16.01.2017 50
Technical Sanction Order Number Dated Amount(crores)
RBDCK/T 42/TS-07/2020-21 15.02.2021 48.52
Revised Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.1066/2017/PWD 22.07.2017 63.86
District Malappuram
LAC Tirur , Thavanur
Project Details
Actual Start Date 28.04.2023
Contractor(s) Uralungal Labour Contract Co-operative Society Ltd
Project Management Consultant RITES
Category River Bridges
Length including approaches 1180
Width of Bridge 11
No of Lanes 2
Financial Details
AS Amount(crores) 50
Revised AS Amount(crores) 63.86
Funded By KIIFB
Project Outlay(crores) 53.38
TS Amount(crores) 48.52
Tender Details
Tender No Dated Tender Amount(crores)
RBDCK/ T42/132 / 2021 05.08.2021 42.88
Agreement Details
Agreement No Agreement Date Agreed Amount(crores) Site Handover Date Period of Completion Actual Date of Completion
RBDCK/T 42/74/2023 20.04.2023 48.83 28.04.2023 18 months
Work Progress Details
Current status Agreement was executed with M/s ULCCS for an amount of Rs. 48.83 Cr on 20.04.2023. NTP issued on 28.04.2023. GoK is planning to use UHPFRC (ULTRA HIGH PERFORMANCE FIBRE REINFORCED CONCRETE) technology for new bridge construction in Kerala and RBDCK has planned to adopt this Technology in the construction Thirunnavaya Bridge. GoK directed to form, Advisory Committee, Implementation Committee & Technical Committee. Accordingly RBDCK had formed Implementation Committee and Technical Committee. Preparation of Design & drawings is completed and submitted to TS committee. Initial pile load test completed. Technical committee was convened on 16.08.2024 & 18.10.2024. Regarding the alignment of Thirunavaya –Thavanur River bridge a petition was submitted on Hon'ble High Court by Dr. E Sreedharan. Hon'ble High Court directed on 03.10.2024 that the PWD Secretary will examine the suggestions given by the Petitioner and thereafter taken an appropriate decision. Accordingly RBDCK had requested PWD Secretary to hear petitioner at the earliest. PWD Secretary visited site & heard Dr. E Sreedharan on 26.11.2024. During the hearing, Dr. E. Sreedharan proposed a new alignment option that differed from the option submitted by Dr. E. Sreedharan to the Hon'ble court. Based on this suggestion, the Secretary, PWD directed RBDCK to study the new alignment and show this to Dr. E. Sreedharan.As per the direction of Secretary, PWD, RBDCK has prepared new alignment sketche and a comparison reports were shown to Dr. E. Sreedharan on 19.12.2024 and same report was submitted on 23.12.2024 to Secretary, PWD. Government has decided to reject Dr. E Sreedharan's request for an alignment change on 11.03.2025. Accordingly RBDCK directed M/s ULCCS to start the work on 20.03.2025.