Projects

Melechovva Flyover

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.1324/2016/PWD 27.09.2016 30
Technical Sanction Order Number Dated Amount(crores)
RBDCK/ T 159/ TS - 07/ 2023-24 29.01.2024
Revised Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.161/2023/PWD 16.02.2023 28.68
District Kannur
LAC Kannur
Project Details
Contractor(s)
Category Flyover
Length including approaches 418.39 m
Width of Flyover 10 m (Overall 24 m)
No of Lanes 2 Lane with service road on both side
Financial Details
AS Amount(crores) 30
Revised AS Amount(crores) 28.68
Funded By KIIFB
Project Outlay(crores) 27.59
Tender Details
Tender No Dated Tender Amount(crores)
RBDCK/ FLY/ T 159/319/2024 11.06.2024 24.54
Work Progress Details
Current status KIIFB approved DPR for Melechovva Underpass on 20.01.2018 for an amount of Rs.27.59 Cr. NOC obtained from NHAI on 12.10.2021. The entire land (57.45Cents) was taken possession on 20.12.2021. The Government issued Administrative Sanction for the Melechovva flyover on 16.02.2023. The revised estimate and alignment were submitted to KIIFB, and financial sanction (Rs. 44.71 Cr) was received on 11.10.2023. TS committee was held on 29.01.2024 and recommended to issue technical sanction for the estimate amounting to Rs. 31,98,58,890.41. The work was tendered on 23.02.2024, and the technical bid was opened on 18.04.2024, receiving a single bid. The work was retendered on 12.06.2024, and the pre-qualification bid was opened on 02.08.2024. After evaluation, the tender committee meeting was conducted on 11.09.2024, and the financial bid was opened on 12.09.2024, with M/s ULCCS quoting the lowest amount (24.54 crores + GST). Revised LOA issued on 27.11.2024. Agreement was executed on 21.01.2025. NTP issued on 03.02.2025. Geotechnical investigation started on 27.02.2025 for design work. In parallel, a requisition for additional land for the flyover was submitted to the District Collector. Boundary stone planting was completed, and a joint inspection was conducted on 27.07.2024. KIIFB and the Tahsildar submitted a feasibility report on 23.09.2024. Revenue AS not received so far (Requested PWD secretary on 12.03.2024).