General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.1324/2016/PWD | 27.09.2016 | 10 | |
District | Ernakulam | ||
LAC | Aluva |
Project Details | |
---|---|
LA status | |
Project Management Consultant | KITCO Ltd |
Category | Road Over Bridges |
LC No | 64B |
Railway (km) | 85/12-13 |
Length Including Approaches | 916.80 |
Width of ROB | 10.15 |
GAD Status | Not approved |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 10 |
Funded By | KIIFB |
Project Outlay(crores) | 45.67 |
Work Progress Details | |||
---|---|---|---|
Current status | DPR approved by KIIFB on 19.03.2018 for an amount of Rs.45.67 Cr. GAD approved on 31.07.2023. MOU with RBDCK and Railways was executed. Tender invited on 06.07.2024. Technical Bid opened on 29th August 2024. No Bid received. Re-tender invited and technical bid opened on 07.11.2024. Technical evaluation is in progress. |