General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.1324/2016/PWD | 27.09.2016 | 10 | |
District | Ernakulam | ||
LAC | Aluva |
Project Details | |
---|---|
Actual Start Date | 14.06.2018 |
Project Management Consultant | KITCO Ltd |
Category | Road Over Bridges |
LC No | 64B |
Railway (km) | 85/12-13 |
Length Including Approaches | 916.80 |
Width of ROB | 10.15 |
GAD Status | Not approved |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 10 |
Funded By | KIIFB |
Project Outlay(crores) | 45.67 |
Work Progress Details | |||
---|---|---|---|
Physical progress | 52 % | ||
Current status | DPR approved by KIIFB on 19.03.2018 for an amount of Rs.45.67 Cr. LA requisition submitted on 28.06.2018. 11(1) Notification published on 03.03.2021. 19(1) declaration published on 22.02.2022. 54 out of 55 cases handed over to RBDCK on 08.12.2023. Balance cases has to be handed over to RBDCK from LAO. GAD approved on 31.07.2023. TS for construction issued on 08.02.2024. TS estimate submitted to KIIFB for approval. |