General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.1324/2016/PWD | 27.09.2016 | 20 | |
Technical Sanction | Order Number | Dated | Amount(crores) |
RBDCK/T 203/TS-04/2022-23 | 01.08.2022 | 33.54 | |
Revised Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.878/2018/PWD | 19.05.2018 | 80.42 | |
District | Kottayam | ||
LAC | Kanjirappally |
Project Details | |
---|---|
Actual Start Date | 10.08.2023 |
Contractor(s) | Backbone Construction Pvt. Ltd. |
Project Management Consultant | RITES |
Category | Road Projects |
Length | 1.626 km |
Right of way | 14.00m |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 20 |
Revised AS Amount(crores) | 80.42 |
Funded By | KIIFB |
Project Outlay(crores) | 78.69 |
TS Amount(crores) | 33.54 |
Tender Details | |||
---|---|---|---|
Tender No | Dated | Tender Amount(crores) | RBDCK/RW/T203/207/2022 | 25.11.2022 |
Agreement Details | |||||||
---|---|---|---|---|---|---|---|
Agreement No | Agreement Date | Agreed Amount(crores) | Site Handover Date | Period of Completion | Actual Date of Completion | ||
RBDCK/T 203/78/2023 | 03.08.2023 | 26.16 | 10.08.2023 | 18 |
Work Progress Details | |||
---|---|---|---|
Physical progress | 10 % | ||
Current status | LOA issued on 10.05.2023 and agreement executed on 03.08.2023 for an amount of Rs. 26,16,74,673.48/-. NTP issued on 10.08.2023. Preliminary works are in progress (initial survey works, preparation of design & drawings, clearing & grubbing etc. Earthwork excavation & filling works in progress. Arrangements for test pile for the bridge portion is in progress. |