Projects

Kanjirapalli Bypass

Back View Alignment

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.1324/2016/PWD 27.09.2016 20
Technical Sanction Order Number Dated Amount(crores)
RBDCK/T 203/TS-04/2022-23 01.08.2022 33.54
Revised Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.878/2018/PWD 19.05.2018 80.42
District Kottayam
LAC Kanjirappally
Project Details
Actual Start Date 10.08.2023
Contractor(s) Backbone Construction Pvt. Ltd.
Project Management Consultant RITES
Category Road Projects
Length 1.626 km
Right of way 14.00m
No of Lanes 2
Financial Details
AS Amount(crores) 20
Revised AS Amount(crores) 80.42
Funded By KIIFB
Project Outlay(crores) 78.69
TS Amount(crores) 33.54
Tender Details
Tender No Dated Tender Amount(crores)
RBDCK/ RW/ T203/ 237/ 2023 13.03.2023 26.6
Agreement Details
Agreement No Agreement Date Agreed Amount(crores) Site Handover Date Period of Completion Actual Date of Completion
RBDCK/T 203/78/2023 03.08.2023 26.16 10.08.2023 18
Work Progress Details
Physical progress 10 %
Current status Preliminary works are in progress (initial survey works, preparation of design & drawings, clearing & grubbing etc.) Earthwork excavation, filling, hard rock excavation and culvert works are in progress.
View Alignment