Ottappalam Bypass

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.1324/2016/PWD 27.09.2016 15
District Palakkad
LAC Ottapalam
Project Details
Actual Start Date 04.09.2018
Project Management Consultant KITCO Ltd
Category Road Projects
Length 1.814 km
Right of way 15 m
No of Lanes 2
Financial Details
AS Amount(crores) 15
Funded By KIIFB
Project Outlay(crores) 78.05
Work Progress Details
Physical progress 52 %
Current status DPR approved on 15.05.2018. LA requisition submitted on 4.09.2018. Boundary stone planting completed and Site inspection conducted. 4(1) notification published on 03.12.2019. 11(1) Notification published on 18.02.2021. Joint verification by LAO and RBDCK officials was conducted on 09.12.2021 & 14.12.2021. As per G.O(P) No.364/2022/RD dated 08.04.2022, the time for publication of 19(1) declaration was extended for 6 months from 18.02.2022. LA cost released to LAO on 23.07.2022. 19(1) declaration published on 12.08.2022. 76% of Land possession is completed. Balance is in progress.