| Current status |
DPR approved by KIIFB on 26.10.2018. Land taking possession completed on 21.12.2023. GAD approved by Railways on 10.01.2024. Railway has accorded permission to execute the work on single entity basis.
Land transfer of 0.77 Are of Vellamanal HSS completed on 14/02/2025.
TS was issued on 14.10.2024. Estimate submitted to KIIFB for revised FS. Tender will be invited after getting approval of revised FS. Since DSoR 2021 has been implemented, estimate is revised and submitted to KIIFB on 18.08.2025. Revised FS is obtained on 15.12.2025.
Request submitted to Railways for informing the amount to be deposited to Railways vide letter dated 26.06.2024 and reminder submitted on 04.11.2024. Also reminder request submitted on 23.10.2025 and requested a confirmation regarding adoption of SV loading and Intimation of Deposit charges. Awaiting reply from Railways. |