General Details
Administrative Sanction Order Number Dated Amount(crores)
GO (Rt)No.942/2017/PWD 10.07.2017 50
District Kollam
LAC Eravipuram
Project Details
Actual Start Date 24.12.2018
Project Management Consultant KITCO Ltd
Category Road Over Bridges
LC No 551
Railway (km) 163/900-164/000
Length Including Approaches 386.00
Width of ROB 10.20
GAD Status Not approved
No of Lanes 2
Financial Details
AS Amount(crores) 50
Funded By Government
Project Outlay(crores) 25.945
Work Progress Details
Physical progress 60 %
Current status DPR approved by KIIFB on 26.10.2018. Land taking possession completed on 21.12.2023. GAD approved by Railways on 10.01.2024. Railway has accorded permission to execute the work on single entity basis. Land transfer of 0.77 Are of Vellamanal HSS completed on 14/02/2025. TS was issued on 14.10.2024. Estimate submitted to KIIFB for revised FS. Tender will be invited after getting approval of revised FS. Since DSoR 2021 has been implemented, estimate is revised and submitted to KIIFB on 18.08.2025. Revised FS is obtained on 15.12.2025. Request submitted to Railways for informing the amount to be deposited to Railways vide letter dated 26.06.2024 and reminder submitted on 04.11.2024. Also reminder request submitted on 23.10.2025 and requested a confirmation regarding adoption of SV loading and Intimation of Deposit charges. Awaiting reply from Railways.