Current status |
DPR approved by KIIFB on 26.10.2018. LA Taking Possession Completed on 21.12.2023. GAD approved by Railways on 10.01.2024. Railway has accorded permission to execute the work on single entity basis.
Land transfer of 0.77 Are of Vellamanal HSS completed on 14/02/2025.
TS was issued on 14.10.2024. Estimate submitted to KIIFB for revised FS. Tender will be invited after getting approval of revised FS. Since, DSoR 2021 has been implemented estimate is being revised.
Request submitted to Railways for informing the amount to be deposited to Railways vide letter dated 26.06.2024 and reminder submitted on 04.11.2024. Awaiting reply from Raiwlays. |