Current status |
DPR approved by KIIFB on 26.10.2018. LA Taking Possession Completed on 21.12.2023. GAD approved by Chief Bridge Engineer on 10.01.2024. Railway has accorded permission to execute the work on single entity basis.
Land transfer of 0.77 Are of Vellamanal HSS is required for the construction of ROB. Request for land transfer along with NOC from General education department and Requisition submitted to district collector on 09.08.2024.
TS committee approved estimate & accorded TS on 14.10.2024. Estimate submitted to KIIFB for revised FS on 28.11.2024. Tender will be invited after getting approval of revised FS. |