Projects

Vallapuzha ROB

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
G.O. (Rt)No.771/2018/PWD 27.04.2018 22.66
District Palakkad
LAC Pattambi
Project Details
Actual Start Date 16.08.2019
Project Management Consultant KITCO Ltd
Category Road Over Bridges
LC No 4
Railway (km) 10/300-400
Length Including Approaches 423.13
Width of ROB 10.20
No of Lanes 2
Financial Details
AS Amount(crores) 22.66
Funded By KIIFB
Project Outlay(crores) 23.28
Work Progress Details
Physical progress 10 %
Current status LA in progress. 4(1) notification published on 30.09.2021. SIA final report published on 30.11.2021. Expert committee report submitted to DC Palakkad. 11(1) notification published on 15.03.2022. Subdivision survey completed. BVR prepared. DVS passed by DC. LA fund sanctioned by KIIFB on 05.08.2022. 19(1) published on 11.10.2022. Entire land taken possession was completed on 27.02.2023. GAD was approved in 2014. But on 29.03.2023, Railway had directed to revise the GAD by adopting RDSO standard span of 30m. Hence revised final GAD & Alignment submitted to Railways on 17.05.2023. Railway recommended some modification and the same was submitted on 23.01.2024. Awaiting approval of GAD from Railways. The work may be tendered after the approval from Railways.