Current status |
DPR approved by KIIFB on 11.02.2020 for an amount of Rs.62.11 Cr. LA Requisition submitted on 19.06.2020. 4(1) notification published on 06.08.2021. 11(1) notification published on 03.08.2022. 19(1) notification published on 21/02/2024. Land taken possession 65/69 completed. Balance pending due to WP(C) 39771/2022. Joint Inspection with KSEB and KWA regarding utility shifting completed on 24/05/2024.
TS committe was held on 30.10.2024 and recommented to issue technical sanction for the estimate amounting to Rs. 72,96,45,445.20. Revised F.S issued by KIIFB on 23.03.2025. Work tendered on 29.03.2025. Technical bid opened on 17.05.2025 and 3 bids received. Financial bid opened on 06.06.2025. Negotiation letter issued to ULCCS. ULCCS has informed that they are not able to reduce the quoted amount. Now, negotiation issued to L1 bidder. |