General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO (Rt)No.942/2017/PWD | 10.07.2017 | 30 | |
District | Kollam | ||
LAC | Karunagapally |
Project Details | |
---|---|
Actual Start Date | 24.12.2018 |
Project Management Consultant | KITCO Ltd |
Category | Road Over Bridges |
LC No | 50 |
Railway (km) | 126/366 |
Length Including Approaches | 582.72 m |
Width of ROB | 10.20 m |
GAD Status | Approved |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 30 |
Funded By | KIIFB |
Project Outlay(crores) | 28.5 |
Work Progress Details | |||
---|---|---|---|
Physical progress | 80 % | ||
Current status | DPR approved on 26.10.2018 for an amount of Rs.28.5 Cr. Land taking possession completed on 16.10.2023. GAD approved by Railways on 08.08.2022. Land transfer of Government land completed on 26.07.2024. TS committee approved estimate and accorded Technical Sanction on 29.01.2024. KIIFB accorded revised financial sanction on 27.11.2024. Tender Document is under preparation. |