| Current status |
Land acquistion completed on 16.01.2023.
The existing AS was for an amount of Rs. 10.30 Cr based on DSR 2016. Hence, Request submitted to Secretary PWD for the revised AS on 14.07.2022 for an amount of Rs. 12.82 crores (based on DSR 2018). Secretary PWD enquired some clarifications and reply for the same was submitted on 02.12.2022, 04.01.2023, 14.02.2023 & 07.06.2023. Letter enquired some clarifications received from GoK on 01.02.2024 and reply for the same is submitted on 07/02/2024. Revised AS from GoK received (GO (Rt) No 674/2024/PWD dated 04.07.2024. Appointed M/s RITES for the design of Pavangad ROB. Design and drawings submitted to IITM for proof checking. Proof checked drawing from IIT has received. Since DSR 2021 came in effect, estimate has been revised which results in 7.4% increase in estimate maount. Revised AS obtained on 26.07.2025. TS Sanctioned on 29.08.2025. Work was tendered on 22.09.2025 and again retendered on 06.11.2025. Technical bid opened on 20.12.2025. 2 bids received. Finacial bid opened on 08.12.2025. LOA issued to TANB Constructions on 24.01.2026. Foundation stone laying ceremony was conducted on 14.02.2026.
|