Weekly Progress From 09.08.2021 - 14.08.2021 | ||||
---|---|---|---|---|
Sl No | Item Description | Executed Quantity | Remarks | |
1 | Initial Pile load test completed. | |||
2 | Utility Shifting Work in Progress | |||
3 | Survey works - Initial ground levels taken and Marking Pile coordinates and Pile cap coordinates for pier P1, P2, P3, P4, P5 | |||
4 | Working Pile started boring started on12.08.2021 at location Pier 01/Pile No.:02. Boring is in progress |